Winery
New building
2009 (completion date)
Client: Alfred Bonnie.
Project design: Eliana Bórmida y Mario Yanzón, architects.
Project manager: Gustavo Albera, architect.
Site managers: Gustavo Albera y AgustÃn Palmada, architects.
Team: AgustÃn Palmada, Alejandro Cohen, Mauricio Cremaschi, Germán Reig, Laia Reynals, Silvana Sevilla and Juan Manuel Schenone architects.
Interior design: Bórmida & Yanzón: Ana Paula Schmidt, Eliana Palmieri, architects.
Structural Engineer: Juan Camps y Asociados, engineers.
Main Contractor: Santiago Monteverdi Construcciones Civiles S.A.
Total area: 110 hectares.
Built area: 12.500 m2
Landscaping: Eduardo Vera.
Capacity: 1.200.000 lts.
Website: www.diamandes.com
Location: Clodomiro Silva S/N. Vista Flores, Tunuyán, Mendoza, Argentina.
Â